"Construction of a section of combined sewer in the area of Komuny Paryskiej and Szczanieckiej Street in Szczecin."
As part of the construction of the sewage network, the following works were carried out:
GRP pipe SN 10000 Dn 600mm - 9.4 mm
GRP pipe SN 10000 Dn 1000mm - 69.0 mm
Microtunneling with GRP Dn 1200mm as protective pipe - 46.5 m
Microtunneling from GRP Dn 1000mm -SN 80000 - 100.2 m
Microtunneling - 2 stark chambers and 1 receiving chamber)
GRP chambers DN 1200mm - 4 pcs
Reinforced concrete chamber D4 rectangular cascade cast from B37 - 1 pc
D6 partition reinforced concrete chambers, cast from B37 wet with five sides, with a stainless steel valve Dn 600mm - 1 pc
|